PROJECT INFORMATION

Region : Mary, Turkmenistan
Construction Period : 26 months
Start Date : October 2011
Date of Completion : December, 2013
Employer : Renaissance Heavy Industries

Scope of Works
• Structural Steel Erection Works (4200 ton)
• Piping Prefabrication Works (2000 ton)
• Piping Erection Works (650 ton)
• Pannel Cladding Works (Sandwich and Trapeze) (7500 m2)
• Equipment Erection Works (650 ton) such as,
– Air Cooled Heat Exchangers
– Bagging Building
– Conveyor System
– Overhead Crane